据安迅思3月19日消息称,3月18日,英国石油巨头英国石油公司宣布,计划在2030年之前在蒂赛德产业群建设1吉瓦的蓝氢设施。
这个名为H2Teesside的项目将占英国政府雄心勃勃的目标的20%,即在这个十年结束前实现5GW的低碳氢生产。该设施将使用天然气以及碳捕获和存储来产生蓝氢。
该项目将在2024年做出最终投资决定后分阶段建设。此后,到2027年或更早的时候,500兆瓦的装机容量可能会上线,剩余的装机容量可能会在2030年上线。
拟议的H2Teesside工厂的碳捕获率高达98%。
英国石油公司没有说明这项技术是将采用自动热重整(ATR)还是蒸汽甲烷重整(SMR)。
ATR是苏格兰Acorn项目和大曼彻斯特地区的HyNet项目的首选技术。
英国石油公司表示,H2Teesside项目生产的氢气将用于工业区,但随着时间的推移,也可以分配到居民区。
与此同时,BP与Venator签署了一份谅解备忘录,为其旗舰产品二氧化钛(TiO2)颜料和性能添加剂供应氢气。
此外,与英格兰北部的天然气分销商北部天然气网络公司(NGN)签署了一份谅解备忘录,以向工业和住宅用户提供脱碳天然气供应。
H2Teesside将与该地区的净零Teesside(BZT)和Northern Endurance Partnership(NEP)碳捕集利用与封存(CCUS)项目整合,这两个项目均由BP作为运营商领导。
在此之前,英国政府于3月17日发布了工业脱碳战略,该战略将提供1.71亿英镑资金,以减少包括蒂赛德在内的几个产业集群的排放。
朱佳妮 摘译自 安迅思
原文如下:
BP announces 1GW blue hydrogen project
On 18 March British oil major BP announced plans for a 1GW blue hydrogen facility at Teesside industrial cluster by 2030.
The project, called H2Teesside, would account for 20% of the UK government’s ambition to have 5GW of low-carbon hydrogen production online by the end of this decade. The facility would use natural gas alongside carbon capture and storage to generate blue hydrogen.
The project will be built in phases following final investment decision, which is due to be taken in 2024. Thereafter, 500MW of capacity could be online by 2027 or earlier, with the remaining capacity potentially online by 2030.
Carbon capture rates from the proposed H2Teesside plant are as high as 98%.
BP doesn’t state whether the technology will be autothermal reforming (ATR) or steam methane reforming (SMR).
ATR is the technology of choice for both the Acorn project in Scotland and the HyNet project around the greater Manchester region.
According to BP, the hydrogen from the H2Teesside project will be used within the industrial region, but could also be distributed to residential areas with time.
In line with this, BP has signed a Memorandum of Understanding (MoU) with Venator to supply hydrogen to its flagship titanium dioxide (TiO2) pigments and performance additives.
A further MoU was signed with Northern Gas Networks (NGN), the gas distributor for the North of England to provide decarbonised gas supply to industrial and residential customers.
H2Teesside would be integrated with the region’s Net Zero Teesside (BZT) and Northern Endurance Partnership (NEP) carbon capture use and storage (CCUS) projects, both of which are led by BP as operator.
This announcement follows the UK Government’s Industrial Decarbonisation Strategy released on 17 March, which will provide £171m in funding to reduce the emissions produced by several industrial clusters, including Teesside.