据天然气资讯4月7日消息称,切尼尔能源公司宣布,科珀斯克里斯蒂(Corpus Christi)液化项目的第3条生产线已于2021年3月26日完成。调试工作已经完成,切尼尔的EPC合作伙伴贝克特尔石油天然气和化工有限公司已将3号生产线的照管、保管和控制移交给切尼尔。
切尼尔其子公司和贝克特尔已经宣布,科珀斯克里斯蒂液化项目和塞宾帕斯液化项目共八条液化生产线在每条生产线保证完工日期之前并在项目预算范围内实质性完成。
随着项目的实质性完成,未来3号生产线的液化天然气销售的财务结果将反映在切尼尔及其附属公司的运营报表中。
朱佳妮 摘译自 天然气资讯
原文如下:
Substantial completion of Train 3 at liquefaction project announced by Cheniere
Cheniere Energy, Inc. (Cheniere) has announced that Substantial Completion of Train 3 at the Corpus Christi liquefaction project was achieved on 26 March 2021. Commissioning is complete and Cheniere’s EPC partner Bechtel Oil, Gas and Chemicals, Inc. (Bechtel) has turned over care, custody, and control of Train 3 to Cheniere.
Cheniere, its subsidiaries, and Bechtel have now declared Substantial Completion on a total of eight liquefaction trains at the Corpus Christi liquefaction project and the Sabine Pass liquefaction project ahead of each train’s guaranteed completion date and within project budgets.
With the achievement of Substantial Completion, financial results of LNG sales from Train 3 going forward will be reflected in the statement of operations of Cheniere and its applicable affiliates.