雪佛龙推进澳大利亚天然气压缩项目

   2021-07-13 互联网讯

58

核心提示:   据世界天然气7月5日消息称,作为Gorgon 合资企业的运营商,雪佛龙将继续推进位于澳大利亚的价值约 40

   据世界天然气7月5日消息称,作为Gorgon 合资企业的运营商,雪佛龙将继续推进位于澳大利亚的价值约 40 亿美元(60 亿澳元)的 Jansz-Io 压缩 (J-IC) 项目。

  Jansz-Io油田位于西澳大利亚州西北海岸约200公里处,水深约1350米。

  作为对Gorgon现有开发项目的改进,J-IC将包括建设和安装一个27000吨的通常无人管理的浮动现场控制站(FCS),大约6500吨的海底压缩基础设施,以及连接到巴罗岛的135公里海底电缆。

  Gorgon 包括一座年产1560万吨的液化天然气设施,包括三条生产线,一个每天向西澳大利亚供应300太焦耳天然气的国内天然气工厂,该压缩项目一直被设想为Gorgon最初发展计划的一部分。

  雪佛龙公司周五表示,施工和安装活动预计需要大约五年时间才能完成。

  雪佛龙欧亚太平洋勘探和生产总裁Nigel Hearne表示,自2018年批准Gorgon Stage 2项目以来,J-IC是雪佛龙在澳大利亚最重要的资本投资。

  Hearne表示:“利用世界领先的海底压缩技术,J-IC能够保持Jansz-Io油田到巴罗岛现有的三个液化天然气生产线和国内天然气工厂的天然气供应。”

  “这将为客户保持一个重要的清洁天然气来源,使亚太地区国家的能源转型成为可能。”

  曹海斌 摘译自 世界天然气

  原文如下:

  Chevron sanctions $4 billion compression project in Australia

  Chevron Corporation, as the operator and the Gorgon joint venture, will proceed with the approximately $4 billion (AU$6 billion) Jansz-Io Compression (J-IC) project located in Australia.

  The Jansz-Io field is located around 200 kilometres offshore the northwest coast of Western Australia at approximately 1,350 meters below the surface.

  A modification of the existing Gorgon development, J-IC will involve the construction and installation of a 27,000-tonne normally unattended floating Field Control Station (FCS), approximately 6,500 tonnes of subsea compression infrastructure, and a 135km submarine power cable linked to Barrow Island.

  Gorgon comprises a three-train, 15.6 million tonnes per annum LNG facility and a domestic gas plant with the capacity to supply 300 terajoules of gas per day to Western Australia and the compression project was always envisaged as part of the original Gorgon development plans.

  Construction and installation activities are estimated to take approximately five years to complete, Chevron said on Friday.

  Nigel Hearne, Chevron Eurasia Pacific Exploration and Production president, said J-IC represents Chevron’s most significant capital investment in Australia since the sanctioning of the Gorgon Stage 2 project in 2018.

  “Using world-leading subsea compression technology, J-IC is positioned to maintain gas supply from the Jansz-Io field to the three existing LNG trains and domestic gas plant on Barrow Island”, Hearne said.

  “This will maintain an important source of clean-burning natural gas to customers that will enable energy transitions in countries across the Asia Pacific region”.



免责声明:本网转载自其它媒体的文章,目的在于弘扬石化精神,传递更多石化信息,并不代表本网赞同其观点和对其真实性负责,在此我们谨向原作者和原媒体致以敬意。如果您认为本站文章侵犯了您的版权,请与我们联系,我们将第一时间删除。
 
 
更多>同类资讯
  • china
  • 没有留下签名~~
推荐图文
推荐资讯
点击排行
网站首页  |  关于我们  |  联系方式  |  使用说明  |  隐私政策  |  免责声明  |  网站地图  |   |  工信部粤ICP备05102027号

粤公网安备 44040202001354号