据AzerNews网站2021年7月22日报道,近日,阿塞拜疆国家石油公司(SOCAR)在布拉杰尼兹油田投产了第123号高产井。
第123号高产井于2017年在布拉杰尼兹油田钻至6132米深度,迄今为止,这口高产井已产出10.4万吨凝析油和4.72亿立方米天然气。
SOCAR说,“最近,这口高产井的天然气日产量自然递减到了15万立方米,因此必须采取额外措施。作为地质测量结果,该高产井投产时的日产量为120吨凝析油和50万立方米天然气。”
此外,这口高产井预计将运行到2041年。 总的说来,这口高产井预计将生产70多万吨凝析油和30多亿立方米天然气。
布拉杰尼兹油田在1975年被发现。 目前,13口井每天生产约700吨凝析油和300万立方米天然气。 作为全面油田开发计划的一部分,SOCAR计划再钻17口井。 每口井预计将日产100吨凝析油和50万立方米天然气。
李峻 编译自 AzerNews
原文如下:
SOCAR launches high-productive well at Bulla Deniz field
Azerbaijan’s State Oil Company (SOCAR) has put into operation a highly productive well No.123 in the Bulla Deniz field, Day.az has reported.
The well No. 123 was drilled to a depth of 6,132 meters at the Bulla Deniz field in 2017, and to date, it has produced 104,000 tons of condensate and 472 million cubic meters of gas.
“Recently, a natural decline in daily gas production of up to 150,000 cubic meters has been registered at the well, and additional measures have become necessary. As a result of geological measures, the well was put into operation with a flow rate of 120 tons of condensate and 500,000 cubic meters of natural gas,” the company reported.
Moreover, the well is expected to be operated until 2041. Overall, more than 700,000 tons of condensate and over 3 billion cubic meters of gas are expected to be produced.
The Bulla Deniz field was discovered in 1975. Currently, about 700 tons of oil condensate and 3 million cubic meters of gas are produced from 13 wells per day. It is planned to drill 17 more wells as part of a full-scale field development plan. Each well is expected to produce 100 tons of condensate and 500,000 cubic meters of gas per day.
免责声明:本网转载自其它媒体的文章,目的在于弘扬石化精神,传递更多石化信息,并不代表本网赞同其观点和对其真实性负责,在此我们谨向原作者和原媒体致以敬意。如果您认为本站文章侵犯了您的版权,请与我们联系,我们将第一时间删除。