据天然气资讯3月15日消息称,贝克休斯获得了一份由美国维吉Venture Global LNG授予的合同,为美国路易斯安那州普拉克明液化天然气项目的第一阶段提供液化天然气系统。
贝克休斯提供的高效液化生产线系统 (LTS) 采用模块化设计,通过“即插即用”的方式,能够更快地安装,有助于降低建设和运营成本。贝克休斯在其位于意大利的制造和组装工厂为Venture Global LNG生产、测试和运输预制和完全集成的模块化涡轮机械单元。
此外,贝克休斯还将提供现场服务,协助设备的调试。
贝克休斯涡轮机械和工艺解决方案执行副总裁 Rod Christie 说:“我们很高兴继续与Venture Global LNG进行强有力的合作。普拉克明LNG 项目是我们在模块化液化天然气方面的丰富经验的又一个很好的例子,可提供完全集成的压缩和动力解决方案。作为一家能源技术公司,贝克休斯的职责是提供最高效、低碳的技术解决方案,以满足客户的特定需求,而液化天然气是能源未来的关键组成部分。我们看到一个新的液化天然气周期正在出现,预计未来几年需求将保持强劲。”
Venture Global LNG 首席执行官 Mike Sabel 表示:“贝克休斯一直是Venture Global的优秀合作伙伴,我们期待在这种合作关系的基础上,加大普拉克明LNG的建设。”
普拉克明LNG 项目订单之前,贝克休斯曾于2019年为Venture Global的Calcasieu Pass LNG终端提供一份综合LNG技术解决方案的类似合同,该终端也位于路易斯安那州。
朱佳妮 摘译自 天然气资讯
原文如下:
Baker Hughes awarded contract for Plaquemines LNG project
Baker Hughes has been awarded a contract and granted notice to proceed by Venture Global LNG to provide an LNG system for the first phase of the Plaquemines LNG project in Louisiana, US.
The highly-efficient liquefaction train system (LTS) supplied by Baker Hughes is modularised, helping to lower construction and operational costs with a ‘plug and play’ approach that enables faster installation. Baker Hughes manufactures, tests, and transports the pre-assembled and fully integrated modular turbomachinery units for Venture Global LNG at its manufacturing and assembly facilities in Italy.
As part of the scope, Baker Hughes will also provide field services to assist in commissioning of the supplied equipment.
“We are delighted to continue our strong collaboration with Venture Global LNG. The Plaquemines LNG project is another great example of our extensive experience with modular LNG to provide fully integrated compression and power solutions,” said Rod Christie, Executive Vice President of Turbomachinery & Process Solutions at Baker Hughes. “As an energy technology company, Baker Hughes’ role is to provide the most efficient and lower carbon technology solutions to meet our customers specific needs, and LNG is a critical part of the energy future. We see a new LNG cycle emerging and expect demand will remain robust in the coming years.”
“Baker Hughes has been an outstanding partner to Venture Global and we look forward to building on that partnership as we ramp up construction at Plaquemines LNG,” said Mike Sabel, Venture Global LNG CEO.
The Plaquemines LNG project order follows a similar contract for a comprehensive LNG technology solution supplied by Baker Hughes for Venture Global’s Calcasieu Pass LNG terminal in 2019, also in Louisiana.