据烃加工网11月23日报道,位于马来西亚沙捞越地区沿海城市宾图鲁的新的沙捞越石化甲醇项目将代表马来西亚国家石油化工集团甲醇产能向前迈出重要一步。该集团已经是亚太地区的主要生产商,也是世界第四大甲醇生产商,在现有的240万吨甲醇产能基础上,每年将再加工175万吨甲醇。
该新工厂将为沙捞越地区(马来西亚60%的天然气储量位于该地区)带来巨大的经济增长,这得益于该新工厂和Bintulu附加天然气销售设施2提供的直接和间接就业机会,该设施每天将为甲醇生产提供多达168标准立方英尺的天然气。
对于将持续至2023年3月的工厂建设作业,工程邀请Harbour link和Sarens共同合作,利用世界领先的重型运输、工程运输和起重机租赁方面的国际经验,进行陆上重型运输、模块安装、顶升作业和模块重型吊装。为了执行这些任务,两家公司都决定专注于创造当地工作岗位,因此目前90%的团队由当地工人组成。
从2022年4月开始,该工厂48个模块的运输和安装开始,其中35个需要由SPMT(自推进模块运输)安装。萨伦斯技术团队随后对模块进行了顶升操作。每个管架模块必须提升到一定的高度,并由SPMT运输,以更稳定的方式进行作业,并将操作时间降至最低。
一旦前两个阶段完成,萨伦斯团队就继续进行设备和模块的起重工作。为此,在工作区域使用了CC8800-1、CC2800、CC2400起重机等辅助设备。因此,CC8800-1装置负责吊装3个最大重量为558吨的主要立柱,还将负责安装最大重量为560吨的工艺装置模块(PAU模块)。
郝芬 译自 烃加工网
原文如下:
The new methanol plant in Sarawak will almost double Petronas Chemical Group's current production in Malaysia
The new Sarawak Petchem Methanol Project, located in the coastal city of Bintulu, in the Sarawak region of Malaysia, will represent an important step forward in the methanol production capacity of Petronas Chemical Group, which is already the main producer in Asia-Pacific and the fourth in the world, processing an additional 1.75 million tons per year to the 2.4 MMt it’s already capable of producing.
This new plant will provide a major economic boost to the Sarawak region, where 60% of Malaysia's gas reserves are located, thanks to the generation of direct and indirect employment, both for this new facility and for the Bintulu Additional Gas Sales Facility 2, which will provide up to 168 standard cubic ft of natural gas per day for methanol production.
For the plant's construction operation, which will last until March 2023, Samsung Engineering decided to call on the joint work of Harbour-link and Sarens, taking advantage of the international experience of the world leader in heavy lifting, engineered transport and crane rental for the onshore heavy transport, installation of modules, jacking operations and heavy lifting of modules. To carry out these tasks, both companies decided to focus on the creation of local jobs, so that 90% of the team is currently made up of local workers.
Underway since April 2022, the works began with the transport and installation of the 48 modules that make up the factory, of which 35 needed to be installed by SPMT (Self-Propelled Modular Transport). The Sarens technical team then carried out the jacking maneuvers of the modules. Each pipe rack module had to be lifted to a certain height and transported by SPMTs to carry out the job in a more stable way and minimize the operation time.
once the two previous phases were completed, the Sarens team proceeded with the heavy lifting for equipment and modules. For this, CC8800-1, CC2800, CC2400 cranes and other auxiliary equipment were used in the work area. Thus, the CC8800-1 unit was responsible for lifting 3 major columns with a max weight of 558t, and will also be in charge of installing the Process Unit Modules (PAU Modules), with a maximum weight of 560 tons.
免责声明:本网转载自其它媒体的文章及图片,目的在于弘扬石化精神,传递更多石化信息,宣传国家石化产业政策,展示国家石化产业形象,参与国际石化产业舆论竞争,提高国际石化产业话语权,并不代表本网赞同其观点和对其真实性负责,在此我们谨向原作者和原媒体致以崇高敬意。如果您认为本站文章及图片侵犯了您的版权,请与我们联系,我们将第一时间删除。